106 lines
3.1 KiB
ReStructuredText
106 lines
3.1 KiB
ReStructuredText
******
|
|
Design
|
|
******
|
|
|
|
The *Project Module* introduces some new concepts and extends some existing
|
|
concepts:
|
|
|
|
.. _model-project.work:
|
|
|
|
Work Effort
|
|
===========
|
|
|
|
The *Work Effort* concept is used to represent work that must be done for
|
|
projects, or parts of projects.
|
|
|
|
Each *Work Effort* is described by a name and a type, and there is space
|
|
for additional comments to be added when required.
|
|
|
|
The estimated time and effort needed for the work is recorded, and it is also
|
|
possible to track the actual time and effort required.
|
|
|
|
If timesheets are selected to be used, then the time spent on the work can
|
|
be recorded by `Employees <company:model-company.employee>` by creating
|
|
:doc:`Timesheet Lines <timesheet:index>` with the right :doc:`Timesheet Works
|
|
<timesheet:index>`.
|
|
The *Timesheet Works* for the *Work Efforts* are automatically created and
|
|
deleted as needed.
|
|
|
|
The current progress of a project's work and its
|
|
`Work Status <model-project.work.status>` is also recorded.
|
|
|
|
A project's work can be structured by giving work efforts a parent and some
|
|
children, if required.
|
|
|
|
Each *Work Effort* has a type.
|
|
Once a work effort has been created it can be changed to a different type
|
|
if its scope, or the amount of work required, changes.
|
|
|
|
.. seealso::
|
|
|
|
Work efforts can be found by opening the main menu item:
|
|
|
|
|Projects --> Configuration --> Works Efforts|__
|
|
|
|
.. |Projects --> Configuration --> Works Efforts| replace:: :menuselection:`Projects --> Configuration --> Works Efforts`
|
|
__ https://demo.tryton.org/model/project.work
|
|
|
|
.. _concept-project.work.project:
|
|
|
|
Project
|
|
-------
|
|
|
|
A *Project* is a type of *Work Effort* that is used for larger and more
|
|
complex work.
|
|
|
|
It can have a `Party <party:model-party.party>` and
|
|
`Party Address <party:model-party.address>`.
|
|
These are used to record who the project is for.
|
|
|
|
.. seealso::
|
|
|
|
A list of projects can be found using the main menu item:
|
|
|
|
|Projects --> Projects|__
|
|
|
|
.. |Projects --> Projects| replace:: :menuselection:`Projects --> Projects`
|
|
__ https://demo.tryton.org/model/project.work;name="Projects"&domain=[["type"%2C"%3D"%2C"project"]]
|
|
|
|
.. _concept-project.work.task:
|
|
|
|
Task
|
|
----
|
|
|
|
A *Task* is a type of *Work Effort* that is used for smaller pieces of work.
|
|
|
|
.. seealso::
|
|
|
|
A list of tasks can be found using the main menu item:
|
|
|
|
|Projects --> Tasks|__
|
|
|
|
.. |Projects --> Tasks| replace:: :menuselection:`Projects --> Tasks`
|
|
__ https://demo.tryton.org/model/project.work;name="Tasks"&domain=[["type"%2C"%3D"%2C"task"]]
|
|
|
|
.. _model-project.work.status:
|
|
|
|
Work Status
|
|
===========
|
|
|
|
The *Work Status* concept is used to define the different stages that a
|
|
project's `Work <model-project.work>` goes through.
|
|
|
|
Each status can be used with one, or more, types of work.
|
|
|
|
The progress set on the work status defines the minimum amount of progress
|
|
needed for work to have that status.
|
|
|
|
.. seealso::
|
|
|
|
The available *Work Statuses* are found using the main menu item:
|
|
|
|
|Projects --> Configuration --> Work Status|__
|
|
|
|
.. |Projects --> Configuration --> Work Status| replace:: :menuselection:`Projects --> Configuration --> Work Status`
|
|
__ https://demo.tryton.org/model/project.work
|