Production Work Module
|
|
######################
|
|
|
|
The production work module allows to manage work order for each production.
|
|
It also adds in the production cost for the work cost.
|
|
|
|
Work Center
|
|
***********
|
|
|
|
Work center are places in the warehouse where production operations are
|
|
performed. They can be organized in a tree structure and each center can be
|
|
linked to a category. A cost can be defined on the work center with two
|
|
methods: `Per Cycle` or `Per Hour`.
|
|
|
|
Work
|
|
****
|
|
|
|
Works define for a production which operation to do at which work center.
|
|
They also contains the number of cycles consumed to perform the operation.
|
|
|
|
The work can be in one of these states:
|
|
|
|
* Request
|
|
|
|
The linked production is still waiting.
|
|
|
|
* Draft
|
|
|
|
The production has started but no cycle was already consumed.
|
|
|
|
* Waiting
|
|
|
|
There are some draft cycles planned.
|
|
|
|
* Running
|
|
|
|
There is at least one running cycle.
|
|
|
|
* Finished
|
|
|
|
All the cycles are done (or cancelled).
|
|
|
|
* Done
|
|
|
|
The production is done.
|
|
|
|
The works are created on the waiting production using the linked routing. For
|
|
each step of the routing, a work is created with the operation. The work center
|
|
is set if the operation has a work center category, by choosing a children work
|
|
center of this category. Or if the operation has no category, it is the
|
|
production work center that is used.
|
|
|
|
Cycle
|
|
*****
|
|
|
|
Cycles are used to count the consumption and the duration of the work. It also
|
|
records the effective cost from the work center.
|
|
|
|
The cycle can be in one of this states:
|
|
|
|
* Draft
|
|
* Running
|
|
* Done
|
|
* Cancelled
|