Files
tryton/modules/project_plan
Cédric Krier 98cbb23f58 Improve setup.py
get_required_version does not need to use .dev0 suffix anymore.
The download URL must be empty for development version.
Source Code must point to Heptapod repository.
Foundation email is used as author email.
2022-12-24 13:45:10 +01:00
..
2022-12-16 16:58:02 +01:00
2022-12-16 16:58:02 +01:00
2022-12-16 16:58:02 +01:00
2022-12-16 16:58:02 +01:00
2022-12-16 16:58:02 +01:00
2022-12-16 16:58:02 +01:00
2022-12-16 16:58:02 +01:00
2022-12-16 16:58:02 +01:00
2022-12-16 16:58:02 +01:00
2022-12-16 16:58:02 +01:00
2022-12-16 16:58:02 +01:00
2022-12-24 13:45:10 +01:00
2022-12-16 23:16:08 +01:00
2022-12-16 16:58:02 +01:00
2022-12-16 16:58:02 +01:00
2022-12-16 16:58:02 +01:00

Project Plan Module
###################

The Project Plan module adds planning features on top of the Project
module.


Allocation
**********

An allocation links together an employee, a task and a percentage. It
defines which part of his time the employee should dedicate to this
task.


Work
****

The Work model is extended to support planning features:

- Tasks dependencies: Each work may have predecessor and
  successors. Predecessor and successor must share the same parent
  project.
- tasks leveling, I.E. automatically delay some task to avoid
  overallocation of resources.
- Early Start and Late End computation: If Constraint Start and
  Constraint End are set on a work, on its parent work or on one of
  the predecessors/successors, the Early Start and Late End dates (but
  also Late Start and Early Finish dates) are computed automatically.
- Resource allocation: Each task may allocate one or more resource
  (I.E. a certain amount of time of an employee).


The *Task Leveling* wizard allow to level a group of tasks to avoid
eventual overallocation of resources, It will delay some tasks
depending on task precedencies and task sequences.