Project Module
|
|
##############
|
|
|
|
The Project module provides the concepts of project and task and the
|
|
basis for simple project management.
|
|
|
|
Work Effort
|
|
***********
|
|
|
|
The Work Effort model is used for creating both projects and tasks. This allows
|
|
for instance to transform a task into a project if it gets bigger and need to
|
|
be split. The following fields are defined on the model:
|
|
|
|
- Name: The name of the Project/Task.
|
|
- Type: Can be *Project* or *Task*.
|
|
- Status: The current status of the work.
|
|
- Parent and Children: Define the tree structure of projects and tasks.
|
|
- Party and Party Address: The optional party (and the contact address) for
|
|
which the project is made. Available on projects.
|
|
- Timesheet, start and end: Allow to enter timesheet for this work.
|
|
- Effort: The estimated effort of a task.
|
|
- Total Effort: Available on projects. Gives the total effort of the sub-tasks
|
|
(I.E. tasks of the project and tasks of the sub-projects) of the current
|
|
project.
|
|
- Progress: The progression on the task.
|
|
- Total Progress: Gives the total of progress of the sub-tasks.
|
|
- Comment: A description.
|
|
|
|
|
|
Work Status
|
|
***********
|
|
|
|
The Work Status defines the possible status of projects and tasks. A minimal
|
|
progress can be defined to enforce on works in this status.
|