Project Plan Module
|
|
###################
|
|
|
|
The Project Plan module adds planning features on top of the Project
|
|
module.
|
|
|
|
|
|
Allocation
|
|
**********
|
|
|
|
An allocation links together an employee, a task and a percentage. It
|
|
defines which part of his time the employee should dedicate to this
|
|
task.
|
|
|
|
|
|
Work
|
|
****
|
|
|
|
The Work model is extended to support planning features:
|
|
|
|
- Tasks dependencies: Each work may have predecessor and
|
|
successors. Predecessor and successor must share the same parent
|
|
project.
|
|
- tasks leveling, I.E. automatically delay some task to avoid
|
|
overallocation of resources.
|
|
- Early Start and Late End computation: If Constraint Start and
|
|
Constraint End are set on a work, on its parent work or on one of
|
|
the predecessors/successors, the Early Start and Late End dates (but
|
|
also Late Start and Early Finish dates) are computed automatically.
|
|
- Resource allocation: Each task may allocate one or more resource
|
|
(I.E. a certain amount of time of an employee).
|
|
|
|
|
|
The *Task Leveling* wizard allow to level a group of tasks to avoid
|
|
eventual overallocation of resources, It will delay some tasks
|
|
depending on task precedencies and task sequences.
|