Files
tryton/modules/project_plan
Cédric Krier 35e4dac5d6 Fix computation of documentation series for odd minor version
(grafted from f4d6cf9d57ce7c69bcde185f933f866c0dd40301)

--HG--
branch : 8.0
2026-04-20 21:23:36 +02:00
..
2025-12-15 18:00:12 +01:00
2022-12-16 16:58:02 +01:00
2022-12-16 16:58:02 +01:00
2026-04-20 20:10:13 +02:00
2026-04-20 20:10:13 +02:00
2022-12-16 16:58:02 +01:00
2022-12-16 16:58:02 +01:00
2026-03-25 19:39:52 +01:00
2026-04-20 21:01:58 +02:00
2022-12-16 16:58:02 +01:00

Project Plan Module
###################

The Project Plan module adds planning features on top of the Project
module.


Allocation
**********

An allocation links together an employee, a task and a percentage. It
defines which part of his time the employee should dedicate to this
task.


Work
****

The Work model is extended to support planning features:

- Tasks dependencies: Each work may have predecessor and
  successors. Predecessor and successor must share the same parent
  project.
- tasks leveling, I.E. automatically delay some task to avoid
  overallocation of resources.
- Early Start and Late End computation: If Constraint Start and
  Constraint End are set on a work, on its parent work or on one of
  the predecessors/successors, the Early Start and Late End dates (but
  also Late Start and Early Finish dates) are computed automatically.
- Resource allocation: Each task may allocate one or more resource
  (I.E. a certain amount of time of an employee).


The *Task Leveling* wizard allow to level a group of tasks to avoid
eventual overallocation of resources, It will delay some tasks
depending on task precedencies and task sequences.